Foreman is the construction site captain. He will guide and carry it forward. The main partner of the constructor.
Building permit under the terms of start meeting is to be kept and audits are carried out in the building stages. Construction work on the audit reports and requests should be made by telephone construction supervision. When making orders for the following information: building number, building site location, town, block / farm, rp / RN, the building site and the address of the owner.
After the granting of building permits, and well before the start of construction must be ordered in real estate and by measuring the height of the building site and the status of the country marking. Prior to the construction site to carry out the measurement of the builder to remove the building foundation over the trees, building materials and the potential for dismantling the old buildings or other obstacles to measuring the work. Limit lines shall also be regarded as obstacles to freedom.
When the building foundation or a similar casting has been carried out in measurement and location of the review ordered by phone.
Start Meeting will be held responsible supervisor approval or notification after the building site, as a rule before the start of the building's location is marked in (a sparsely populated area in general audit in connection with the bottom). The meeting date is authorizing the applicant or the responsible supervisor. The initial meeting may be built by permit conditions required by low-rise construction site monitoring book.
To initiate the construction work shall notify the building control and construction site such as a sign.
Audits may also be performed as in many parts. The construction foreman responsible for the audit is required to be present.
The foundation excavation, mining and piling is completed, before any other foundation work begins.
When foundation, a tripod or a similar construction has been completed and the construction of a closed and gravel is installed and 'backs' of pipes are still visible.
When building the frame and load-bearing structures have been and are visible from the outside rather than inside the preparatory work has been undertaken.
Before concealing the chimney.
When the building or part thereof will be introduced before the actual performance of the final review.
When the building is the yard's reputation and the flower beds ready for decision and planning necessary conditions have been met and that all audits successfully completed. In addition, the developer must submit a final audit is the fire authority in the building and approving the protocol as well as construction contractor in the electronic certificate.
Formula areas outside the structure of the sewerage check out the adoption and use of health inspectors.
All construction-related documents, to approve the decision, drawings, a review of records, inspection of construction paper, etc. will remain the most under construction and future needs for a separate folder. During the construction documents will be available on site as needed. Building was finished, the property owner to save documents. Property owner's change of documents must be presented to the new owner.